GETCO Exam Paper (22-07-2015) Differential equation is required to be solved in _____ economical operation of power systems Stability studies Load flow studies Finding efficiency of a transmission line economical operation of power systems Stability studies Load flow studies Finding efficiency of a transmission line ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) "Overshoot" in a time response of control systems is indication of steady state solution measure of relative stability none of this final value of the output steady state solution measure of relative stability none of this final value of the output ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) Steady state stability of a power system is improved by using double circuit line instead of single circuit line reducing fault clearing time by fast switching decreasing generator inertia using double circuit line instead of single circuit line reducing fault clearing time by fast switching decreasing generator inertia ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) Who is the 2012 London Olympics bronze medalist in badminton? Jwala Gutta Sania Ashwini Ponnappa Saina Jwala Gutta Sania Ashwini Ponnappa Saina ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) Which of the following is the most likely reason for large overshoot in a control system? presence of dead time delay High gain in a system high retarding torque high positive correcting torque presence of dead time delay High gain in a system high retarding torque high positive correcting torque ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) An over-current relay of current rating 5 A and setting 150% is connected to a 200/5 A CT. Then the relay to pickup, the line current required is 100 300 200 150 100 300 200 150 ANSWER DOWNLOAD EXAMIANS APP