Construction Planning and Management
Consider the following statements: In the critical path method of construction planning, Free Float can be. 1. Greater than Total Float. 2. Greater than Independent Float 3. Equal to Total Float. 4. Less than Independent Float

1 and 2 are correct
2 and 3 are correct
1 and 4 are correct
1 and 4 are correct

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Mobilization advance up to 10% of the cost of work is given to a contractor

For the purchase of construction materials
For all activities required to start the work at site on finalization of the contract document
For the payment of advances to labour and other staff
On commencement of work at site for payment of loan taken by him

ANSWER DOWNLOAD EXAMIANS APP