Construction Planning and Management
Consider the following activities in a building construction: 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace The correct sequence of these activities is

3, 1, 2, 4
3, 1, 4, 2
1, 3, 2, 4
1, 3, 4, 2

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Free float is mainly used to

Establish priorities
Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities
Identify the activities which can be delayed without affecting the total float of preceding activity
Identify the activities, which can be delayed without affecting the total float of succeeding activity