Construction Planning and Management
Consider the following activities in a building construction: 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace The correct sequence of these activities is

1, 3, 4, 2
1, 3, 2, 4
3, 1, 4, 2
3, 1, 2, 4

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
The reduction in project time normally results in

Decreasing the direct cost and indirect cost both
Increasing the direct cost and indirect cost both
Decreasing the direct cost and increasing indirect cost
Increasing the direct cost and decreasing the indirect cost