Soil Mechanics and Foundation
Clay layer A with single drainage and coefficient of consolidation Cv takes 6 months to achieve 50% consolidation. The time taken by clay layer B of the same thickness with double drainage and coefficient of consolidation Cv/2 to achieve the same degree of consolidation is

3 months
6 months
24 months
12 months

ANSWER DOWNLOAD EXAMIANS APP

Soil Mechanics and Foundation
Coefficient of earth pressure at rest is

less than both the active and passive earth pressures
less than active earth pressure but greater than passive earth pressure
greater than active earth pressure but less than passive earth pressure
greater than both the active earth pressure and passive earth pressure

ANSWER DOWNLOAD EXAMIANS APP