Soil Mechanics and Foundation
Clay layer A with single drainage and coefficient of consolidation Cv takes 6 months to achieve 50% consolidation. The time taken by clay layer B of the same thickness with double drainage and coefficient of consolidation Cv/2 to achieve the same degree of consolidation is

6 months
3 months
12 months
24 months

ANSWER DOWNLOAD EXAMIANS APP

Soil Mechanics and Foundation
Coefficient of earth pressure at rest is

greater than active earth pressure but less than passive earth pressure
less than both the active and passive earth pressures
greater than both the active earth pressure and passive earth pressure
less than active earth pressure but greater than passive earth pressure

ANSWER DOWNLOAD EXAMIANS APP

Soil Mechanics and Foundation
The ultimate consolidation settlement of a structure resting on a soil

Decreases with the decrease in the plastic limit
Decreases with the increase in the initial voids ratio
Increases with the increase in the initial voids ratio
Increases with the decrease in the porosity of the soil

ANSWER DOWNLOAD EXAMIANS APP

Soil Mechanics and Foundation
In hydrometer analysis for a soil mass

both meniscus correction and dispersing agent correction are subtractive
both meniscus correction and dispersing agent correction are additive
meniscus correction is subtractive and dispersing agent correction is additive
meniscus correction is additive and dispersing agent correction is subtractive

ANSWER DOWNLOAD EXAMIANS APP