Estimating and Costing Carpet area does not include the area of The walls along with doors and other openings Bath room and lavatory Kitchen and pantry All of these The walls along with doors and other openings Bath room and lavatory Kitchen and pantry All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is 0.200 m³ 0.295 m³ 0.247 m³ 0.274 m³ 0.200 m³ 0.295 m³ 0.247 m³ 0.274 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by Prismoidal formula, is 3275 m³ 3225 m³ 3300 m³ 3250 m³ 3275 m³ 3225 m³ 3300 m³ 3250 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the correct statement regarding the centre line method of estimating a building Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item All of these The centre line length is reduced by half the layer of main wall joining the partition wall The centre line is worked out separately for different sections of walls of a building Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item All of these The centre line length is reduced by half the layer of main wall joining the partition wall The centre line is worked out separately for different sections of walls of a building ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The minimum width of a septic tank is taken 80 cm 70 cm 75 cm 90 cm 80 cm 70 cm 75 cm 90 cm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The volume is measured correct to the nearest 0.01 cum 0.04 cum 0.03 cum 0.02 cum 0.01 cum 0.04 cum 0.03 cum 0.02 cum ANSWER DOWNLOAD EXAMIANS APP