Industrial Engineering and Production Management
When slack of an activity is negative

All of these
The activity is critical and any delay in its performance will delay the completion of whole project
It represents a situation where extra resources are available and the completion of project is not delayed
It represents that a programme falls behind schedule and additional resources are required to complete the project in time

ANSWER DOWNLOAD EXAMIANS APP

Industrial Engineering and Production Management
The correct sequence of phases in value engineering is

Information phase, creative phase, investigation phase, evaluation phase
Creative phase, investigation phase, evaluation phase, information phase
Investigation phase, information phase, creative phase, evaluation phase
Creative phase, information phase, investigation phase, evaluation phase

ANSWER DOWNLOAD EXAMIANS APP