Industrial Engineering and Production Management The average time recorded by work study man for an operation is called Standard time Representative time Normal time None of these Standard time Representative time Normal time None of these ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management A dummy activity in a net work diagram All of these Is represented by a dotted line Is an artificial activity Does not consume time or resources All of these Is represented by a dotted line Is an artificial activity Does not consume time or resources ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management In process layout Handling and backtracking of materials is too much Production control is more difficult and costly Routing and scheduling is more difficult All of these Handling and backtracking of materials is too much Production control is more difficult and costly Routing and scheduling is more difficult All of these ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management PERT has following time estimate Three time estimate Four time estimate One time estimate Two time estimate Three time estimate Four time estimate One time estimate Two time estimate ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management An activity of the project is graphically represented by ________ on the network diagram. An arrow A straight line None of these A circle An arrow A straight line None of these A circle ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The main disadvantage of line organisation is Structure is rigid Top level executives have to do excessive work All of these Communication delays occur Structure is rigid Top level executives have to do excessive work All of these Communication delays occur ANSWER DOWNLOAD EXAMIANS APP