Power Systems A hydro electric generating station is supplied from a reservoir of capacity 5 × 10 − 6 cubic meters at a head of 200 meters. Find the total energy available in KWh if the overall efficiency is 75 % 4.06 × 106 kWh. 5 × 106 kWh. 2.044 × 106 kWh. 3 × 106 kWh. 4.06 × 106 kWh. 5 × 106 kWh. 2.044 × 106 kWh. 3 × 106 kWh. ANSWER DOWNLOAD EXAMIANS APP
Power Systems Which of the following plants is/are base load plants both 1 and 2 run off river pump storage nuclear both 1 and 2 run off river pump storage nuclear ANSWER DOWNLOAD EXAMIANS APP
Power Systems Where is the draft tube of a hydroelectric plant that is an airtight pipe located In between the runner exhaust and the tail race. In between the penstock and runner. Near the surge tank. At the beginning of the penstock. In between the runner exhaust and the tail race. In between the penstock and runner. Near the surge tank. At the beginning of the penstock. ANSWER DOWNLOAD EXAMIANS APP
Power Systems Four identical alternators each are rated for 20 MVA, 11 KV having a subtransient reactance of 16% are working in parallel. The short circuit level at the busbar is 500 MVA 400 MVA 100 MVA 125 MVA 500 MVA 400 MVA 100 MVA 125 MVA ANSWER DOWNLOAD EXAMIANS APP
Power Systems Thermal shielding is provided to absorb the fast neutron. protected the operating personal from exposure to radiations. prevent the reactor wall from getting heated. All of these absorb the fast neutron. protected the operating personal from exposure to radiations. prevent the reactor wall from getting heated. All of these ANSWER DOWNLOAD EXAMIANS APP
Power Systems Surge impedance loading of a transmission line can be increased by addition of lumped capacitance in series both 1 and 3 addition of lumped inductance in parallel increasing its voltage level addition of lumped capacitance in series both 1 and 3 addition of lumped inductance in parallel increasing its voltage level ANSWER DOWNLOAD EXAMIANS APP