Power Systems
A generating station has a maximum demand of 50 MW a load factor of 60 %, a plant capacity factor of 45 % and if the plant while running as per schedule were fully loaded. The daily energy produced will be

 710 MW.
  720 MW.
 730 MW.
 740 MW.

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
The draft tube is provided to

 raise the water surface of the stream to create an artificial head.
  increase the acting head on the water wheel.
 reduce the effect of water hammer.
None of these