Which turbine is ideally suited to pumped storage plants

  Kaplan.
 Pelton.
 Impeller.
 Francis.

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
IF the time of operation of a relay for unity TMS is 10 sec then the time of operation for 0.5 TMS is

  5 sec.
 20 sec.
 10 sec.
 none of these.

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
Maximum power transfer in a transmission line can be obtained by

 either 1 or 2
 increasing voltage level
None of these
 reducing reactance

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
A loss less transmission line has a length of 600 km, find the phase shift of voltage signal?

 36°
 45°
 42°
 90°

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
Condition for zero voltage regulation is

 tanφ = X/R
 cosφ = R/X
 cosφ = X/R
 tanφ = R/X

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
A power generating station has a maximum demand of 1000 MW. The annual load factor is 75% and plant capacity factor is 60%. Calculate the reserve capacity?

 500 MW
 250 MW
 1250 MW
 750 MW

ANSWER DOWNLOAD EXAMIANS APP
MORE MCQ ON Power Systems

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑