MGVCL Exam Paper (30-07-2021 Shift 2)
Which one of the following is the largest windfarm located in India?

Muppandal
Talcher
Mundra
Vindhayachal

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
A single phase motor connected to 415 V, 50 Hz supply takes 30 A at a power factor of 0.7 lagging. Calculate the capacitance required in parallel with the motor to raise the power factor to 0.9 lagging.

76.32 µF
96.32 µF
66.32 µF
86.32 µF

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
Consider a solar PV plant with the following specific conditions: Analysis period: 1 year
Measured average solar irradiation intensity in 1 year: 120 kWh/m²
Generator area of the PV plant: 10 m²
Efficiency factor of the PV modules: 15%
Electrical energy actually exported by plant to grid: 110 kWh
Calculate the performance ratio.

0.8111
0.5111
0.6111
0.7111

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP