MGVCL Exam Paper (30-07-2021 Shift 3)
Consider a solar PV plant with the following specific conditions:
Analysis period: 1 year
Measured average solar irradiation intensity in 1 year: 150 kWh/m²
Generator area of the PV plant: 10 m² Efficiency factor of the PV modules: 15%
Electrical energy actually exported by plant to grid: 135 kWh
Calculate the performance ratio.

75%
50%
60%
80%

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 3)
Which of the following statements are correct?
(i) Advanced metering infrastructure (AMI) is typically more automated and allows real- time, on-demand interrogations with metering endpoints.
(ii) An Automated Meter Reading (AMR) device only communicates from the customer to the energy supplier.
(iii) AMR meters only provide kWh information and possible peak kW demand for the month.

(i) and (ii) only
(ii) and (iii) only
(i) and (iii) only
(i), (ii) and (iii)

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 3)
The miniature circuit breaker (MCB) with ____ trip characteristics trips instantaneously when the current flowing through it reaches between 10 to 20 times the rated current.

Class Z
Class D
Class B
Class C

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 3)
Murray loop test is performed on a faulty cable 300 m long. At balance, the resistance connected to the faulty core was set at 20 Ω and the resistance of the resistor connected to the sound core was 40 Ω. Calculate the distance of the fault point from the test end.

200 m
100 m
300 m
400 m

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP