When one must sell a project to management, the most important document he or she can produce is a:

None of these
procedure for purchase
method for financing the project
project evaluation
summary of the problem

ANSWER DOWNLOAD EXAMIANS APP

Automation System
The "walk-through" method of programming a robot involves:

None of these
All of these
walking through your suggested procedure with your supervisor prior to programming
physically moving the robot through all the motions it is to repeat
moving the robot from one location to another

ANSWER DOWNLOAD EXAMIANS APP

Automation System
A solenoid:

is related to an aneroid
None of these
can be used only in de circuits
is spring operated
is widely used in industrial automation