Engineering Economics What type of bond where the corporation’s owner name are recorded and the interest is paid periodically to the owners with their asking for it? Callable bond Incorporators bond Registered bond Preferred bond Callable bond Incorporators bond Registered bond Preferred bond ANSWER DOWNLOAD EXAMIANS APP
Engineering Economics The price at which the callable bond will be redeemed from the bondholder is called ______. Face value Call value Redemption value Par value Face value Call value Redemption value Par value ANSWER DOWNLOAD EXAMIANS APP
Engineering Economics If ‘a’ is the base amount expenditure, ‘b’ is the increase in the operation cost each year over a period of’ 'n’ years, the total cost of maintenance is: a - (n - 1) b a + (n + 1) b a + (n - 1) b a × (n - 1) b a - (n - 1) b a + (n + 1) b a + (n - 1) b a × (n - 1) b ANSWER DOWNLOAD EXAMIANS APP
Engineering Economics A machine costs of P 8,000 and an estimated life of 10 years with a salvage value of P 500. What is its book value after 8 years using straight line method? P 2,000.00 P 2,100.00 P 2,200.00 P 2,300.00 P 2,000.00 P 2,100.00 P 2,200.00 P 2,300.00 ANSWER DOWNLOAD EXAMIANS APP
Engineering Economics Pick up the correct reason for making conceptual (or preliminary) estimate from the following: To have a check on a definitive cost estimate To check quotations from contractors and/or sub-contractors To compute target estimate for the owner while drawing and specifications are in initial stage All of these To have a check on a definitive cost estimate To check quotations from contractors and/or sub-contractors To compute target estimate for the owner while drawing and specifications are in initial stage All of these ANSWER DOWNLOAD EXAMIANS APP
Engineering Economics The key to profitable operation for project cost control, is: To keep the project cost equal to original cost estimate To keep the project cost equal to subsequent construction budget None of these To keep the project cost within the cost budget and knowing when and where job costs are deviating To keep the project cost equal to original cost estimate To keep the project cost equal to subsequent construction budget None of these To keep the project cost within the cost budget and knowing when and where job costs are deviating ANSWER DOWNLOAD EXAMIANS APP