The uplift pressure on a dam can be controlled by i) constructing cutoff under upstream face ii) constructing drainage channels bet-ween the dam and its foundation iii) by pressure grouting in foundation The corret answer is

both (i) and (iii)
both (i) and (ii)
only (i)
(i), (ii) and (iii)

ANSWER DOWNLOAD EXAMIANS APP

Irrigation Engineering
Infiltration rate is always

equal to or less than the infiltration capacity
less than the infiltration capacity
more than the infiltration capacity
equal to or more than the infiltration capacity