Building Construction The single stage well point system of dewatering an excavation can be used if the depth of excavation does not exceed 5 m 10 m 20 m 15 m 5 m 10 m 20 m 15 m ANSWER DOWNLOAD EXAMIANS APP
Building Construction The thickness of a reinforced brick partition wall, is generally kept 20 cm 10 cm 15 cm 5 cm 20 cm 10 cm 15 cm 5 cm ANSWER DOWNLOAD EXAMIANS APP
Building Construction The differential settlement in case of foundations on sandy soils should not exceed 100 mm 25 mm 40 mm 65 mm 100 mm 25 mm 40 mm 65 mm ANSWER DOWNLOAD EXAMIANS APP
Building Construction The maximum total settlement for isolated foundations on clayey soils should be limited to 65 mm 25 mm 40 mm 100 mm 65 mm 25 mm 40 mm 100 mm ANSWER DOWNLOAD EXAMIANS APP
Building Construction According to National Building Code, the hydrants in water mains is provided at minimum interval of 75 m 50 m 90 m 60 m 75 m 50 m 90 m 60 m ANSWER DOWNLOAD EXAMIANS APP
Building Construction Auger boring All of these Is generally employed in cohesive and other self soils above water table Is the most primitive method for making a hole in the ground Is most economical up-to a depth of 5 meters All of these Is generally employed in cohesive and other self soils above water table Is the most primitive method for making a hole in the ground Is most economical up-to a depth of 5 meters ANSWER DOWNLOAD EXAMIANS APP