Construction Planning and Management The reduction in project time normally results in Decreasing the direct cost and indirect cost both Increasing the direct cost and indirect cost both Increasing the direct cost and decreasing the indirect cost Decreasing the direct cost and increasing indirect cost Decreasing the direct cost and indirect cost both Increasing the direct cost and indirect cost both Increasing the direct cost and decreasing the indirect cost Decreasing the direct cost and increasing indirect cost ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Preliminary project report for a road project must contain The soil survey, traffic survey, concept design and approximate cost The detailed estimated cost based on detailed design The contract documents for inviting tenders The several alternatives of the project that have been considered The soil survey, traffic survey, concept design and approximate cost The detailed estimated cost based on detailed design The contract documents for inviting tenders The several alternatives of the project that have been considered ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In time-cost optimization of a project, crashing is done. Only on activities lying on the original critical path and having flatter cost slopes On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope On all the activities lying on the critical path On all the activities Only on activities lying on the original critical path and having flatter cost slopes On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope On all the activities lying on the critical path On all the activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Output of a bulldozer is(i) Increased if drawbar HP of the tractor is increased for a given hauling distance(ii) Decreased if drawbar HP of the tractor is increased for a given hauling distance(iii) Increased if the hauling distance is increased for a given drawbar HP of the tractor(iv) Decreased if the hauling distance is increased for a given drawbar HP of the tractor (i) and (iv) are correct (i) and (iii) are correct (ii) and (iii) are correct (ii) and (iv) are correct (i) and (iv) are correct (i) and (iii) are correct (ii) and (iii) are correct (ii) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A machine is purchased for Rs. 10,000,00 and has an estimated life of 10 years. The salvage value at the end of 10 years is Rs. 1,50,000. The book value of the machine at the end of 5 years using general straight line method of evaluation of depreciation is Rs. 5,75,000 Rs. 8,50,000 Rs. 6,50,000 Rs. 4,75,000 Rs. 5,75,000 Rs. 8,50,000 Rs. 6,50,000 Rs. 4,75,000 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following features/factors: 1. Projects are of the non-repetitive type 2. Time required need not be known 3. Time required is known precisely 4. Events have been established for planning 5. Emphasis is given to activities of project PERT is preferred for planning because of 1, 2 and 5 3, 4 and 5 1, 3 and 4 1, 2 and 4 1, 2 and 5 3, 4 and 5 1, 3 and 4 1, 2 and 4 ANSWER DOWNLOAD EXAMIANS APP