Waste Water Engineering The rate of accumulation of sludge per person per year, is 10 litres 15 litres 20 litres 25 litres 10 litres 15 litres 20 litres 25 litres ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering If 2% solution of a sewage sample is incubated for 5 days at 20°C and depletion of oxygen was found to be 5 ppm, B.O.D. of the sewage is 225 ppm 250 ppm 200 ppm None of these 225 ppm 250 ppm 200 ppm None of these ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering The first stage of neutral process of sludge digestion, is None of these Alkaline fermentation Acid fermentation Acid regression None of these Alkaline fermentation Acid fermentation Acid regression ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering For treating the sewage of a large city, you will recommend A plant consisting of Imhoff tanks with low rate trickling filters Sedimentation tanks with high rate trickling filters A sedimentation tank and an activated sludge treatment plant None of these A plant consisting of Imhoff tanks with low rate trickling filters Sedimentation tanks with high rate trickling filters A sedimentation tank and an activated sludge treatment plant None of these ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering The width of a rectangular sewer is twice its depth while discharging 1.5 m/sec. The width of the sewer is 0.88 m 1.76 m 0.68 m 1.36 m 0.88 m 1.76 m 0.68 m 1.36 m ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering For drainage pipes in buildings the test applied before putting them to use, is Water test All listed here Straightness test Smoke test Water test All listed here Straightness test Smoke test ANSWER DOWNLOAD EXAMIANS APP