MGVCL Exam Paper (30-07-2021 Shift 2)
The necessary equation to be solved during the load flow analysis using Fast-Decoupled method is given below:
where B' and B'' are formed using the imaginary part of the bus admittance matrix, Ybus. If the system consists of 6 buses of which one of the bus is slack bus and 2 bues are voltage regulated buses, then then the matrix B' is of order ____and the matrix B'' is of order____, respectivity.
∆P/|Vi| = - B'∆δ
∆Q/|Vi| = - B''∆|V|

3 and 6
5 and 3
3 and 5
6 and 3

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
The magnitude of the generator earth-fault current is limited by

using higher rating CTs
inserting the stabilizing resistance in series with the relay
inserting suitable resistance in neutral grounding circuit
controlling field exciter

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
When different types of consumers are charged at different uniform per unit rates, it is called as ____

flat rate tariff
block rate tariff
two-part tariff
maximum demand tariff

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP