Engineering Economics
The institute of Electronics and Communications Engineers of the Philippines (IECEP) is planning to put up its own building. Two proposals being considered are:A. The construction of the building now to cost P 400,000B. The construction of a smaller building now to cost P300,000 and at the end of 5 years, an extension to be added to cost P 200,000.By how much is proposal B more economical than proposal A if interest rate is 20% and depreciation to be neglected?

P 19,423.69
P 19,122.15
P 19,624.49
P 19,518.03

ANSWER DOWNLOAD EXAMIANS APP

Engineering Economics
The financial analysis:

Helps to judge the success of the firm's financial plans
Helps a bank to know the financial position of the firm for granting a loan to the firm
Helps a share holder to compare the expected return on his investment in the firm against the expected return from other alternative investment
All of these

ANSWER DOWNLOAD EXAMIANS APP