GETCO Exam Paper (22-07-2015) The area under the load duration curve represents average load of the system energy generated in the period considered base load of the system Maximum demand of the power station average load of the system energy generated in the period considered base load of the system Maximum demand of the power station ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) I am looking _____ my pen. Have you seen it? for after to at for after to at ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) In sub stations for making and breaking of load current load interrupter switches are used relays are used isolators are used circuit breakers are used load interrupter switches are used relays are used isolators are used circuit breakers are used ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) In a power system network, at which bus the shunt is connected that can be known from reactive power demand type of bus none of these Y bus of the system reactive power demand type of bus none of these Y bus of the system ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) Which power plant may take several days to start up and shunt down? solar power plant Base load none of these Peak load solar power plant Base load none of these Peak load ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) In G-S method of power flow problem, the number of iterations _____ remains fixed depends on voltage control buses depends on tolerance depends on no of buses remains fixed depends on voltage control buses depends on tolerance depends on no of buses ANSWER DOWNLOAD EXAMIANS APP