Industrial Engineering and Production Management Routing Determines the programme for the operations Is concerned with starting of processes Regulates the progress of job through various processes Prescribes the sequence of operations to be followed Determines the programme for the operations Is concerned with starting of processes Regulates the progress of job through various processes Prescribes the sequence of operations to be followed ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Halsey plan of wage incentive Does not guarantee minimum wage Is applied to all level of workers Is based upon efficiency of worker Is not applied to all level of workers Does not guarantee minimum wage Is applied to all level of workers Is based upon efficiency of worker Is not applied to all level of workers ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The difference between the time available to do the job and the time required to do the job, is known as Float Event Constraint Duration Float Event Constraint Duration ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Positive slack on a PERT indicates that project is Beyond schedule Ahead of schedule As per schedule On critical path Beyond schedule Ahead of schedule As per schedule On critical path ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management What does symbol 'V' employ in work study Permanent storage Operation Delay/ temporary Storage Inspection Permanent storage Operation Delay/ temporary Storage Inspection ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The probability distribution of activity times in PERT follows following distribution Binomial Normal Beta Exponential Binomial Normal Beta Exponential ANSWER DOWNLOAD EXAMIANS APP