Pick up the incorrect statement about advantages of work sampling

Calculations are easier, method is economical and less time consuming
No time measuring devices are generally needed
Simultaneous study of many operators may be made by a single observer
Permits a fine breakdown of activities and delays

ANSWER DOWNLOAD EXAMIANS APP

Industrial Engineering and Production Management
When slack of an activity is positive

It represents that a programme falls behind schedule and additional resources are required to complete the project in time
The activity is critical and any delay in its performance will delay the completion of whole project
Any one of the above
It represents a situation where extra resources are available and the completion of project is not delayed

ANSWER DOWNLOAD EXAMIANS APP

Industrial Engineering and Production Management
Which of the following are the guidelines for the construction of a network diagram?

All of the these
Dummy activity consumes no time or resource
Each activity is represented by one and only one arrow in the network
Dangling must be avoided in a network diagram