Industrial Engineering and Production Management PERT analysis is based upon Most likely time Pessimistic time All of these Optimistic time Most likely time Pessimistic time All of these Optimistic time ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management 'Value' for value engineering and analysis purposes is defined as Function/cost Purchase value Saleable value Depreciated value Function/cost Purchase value Saleable value Depreciated value ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management In Lincoln plan (one type of group incentive plan), the amount of the profit which an employee receives in addition to the guaranteed basic pay/wages, is based on: His individual performance A job evaluation system A merit rating system A standard rating system His individual performance A job evaluation system A merit rating system A standard rating system ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management A big advantage of PERT over Gantt charts is that in the former case Interrelationship among activities is clearly shown Activity times are clear Activities and events are clearly shown Early start and late finish of an activity are clearly marked Interrelationship among activities is clearly shown Activity times are clear Activities and events are clearly shown Early start and late finish of an activity are clearly marked ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Travel charts provide An approximate estimate of the handling which must be done at a particular station A compact estimate of the handling which must be done between various work sections An idea of the flow of materials at various stages The information for changes required in rearranging material handling equipment An approximate estimate of the handling which must be done at a particular station A compact estimate of the handling which must be done between various work sections An idea of the flow of materials at various stages The information for changes required in rearranging material handling equipment ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management If TL is the largest allowable event occurrence time, total activity slack (s) is equal to Latest start time earliest start time TLEFT Latest finish time earliest finish time (EFT) All of these Latest start time earliest start time TLEFT Latest finish time earliest finish time (EFT) All of these ANSWER DOWNLOAD EXAMIANS APP