Power Systems
Merze price current scheme protection is used in

  alternator.
  bus bars.
  transformer.
  both A and B.

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
The fact that current density is higher at the surface when compared to centre is known as

All of these
 skin effect
 proximity effect
 carona

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
A 100 Km long transmission line is loaded at 110 kV. If the loss of line is 5 MW and the load is 150 VA the resistance of the line is

 2.26 Ω / phase.
 4.65 Ω / phase.
  8.06 Ω / phase.
 6.06 Ω / phase.

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
Which of the following power plants needs highly skilled/qualified engineers for its operation

 Thermal.
 Gas-turbine.
 Nuclear.
 Hydro Power Plant

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
For harnessing low variable water heads, the suitable hydraulic turbine with high percentage of reaction and runner adjust vanes is

  Kaplan.
  Francis.
  Pelton.
  Impeller.

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
A power generating station has a maximum demand of 1000 MW. The annual load factor is 75% and plant capacity factor is 60%. Calculate the reserve capacity?

 1250 MW
 500 MW
 250 MW
 750 MW

ANSWER DOWNLOAD EXAMIANS APP
MORE MCQ ON Power Systems

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑