Industrial Engineering and Production Management The bonus increases in proportion to the increase in efficiency. This statement applies to Rowan plan Halsey plan Emerson's efficiency plan Gantt plan Rowan plan Halsey plan Emerson's efficiency plan Gantt plan ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Critical path on PERT/CPM chart is obtained by joining the events having Maximum slack Minimum slack Average slack No slack Maximum slack Minimum slack Average slack No slack ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The time by which the activity completion time can be delayed without affecting the start of succeeding activities, is known as Duration Total float Interfering float Free float Duration Total float Interfering float Free float ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The standard time for a job is Total work content + basic time Total work content Total work content + delay contingency allowance Base time + relaxation time Total work content + basic time Total work content Total work content + delay contingency allowance Base time + relaxation time ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Time study is Machine setting time Method of fixing time for workers The appraisal, in terms of time, of the value of work involving human effort Time taken by workers to do a job Machine setting time Method of fixing time for workers The appraisal, in terms of time, of the value of work involving human effort Time taken by workers to do a job ANSWER DOWNLOAD EXAMIANS APP