Industrial Engineering and Production Management The bonus increases in proportion to the increase in efficiency. This statement applies to Emerson's efficiency plan Halsey plan Rowan plan Gantt plan Emerson's efficiency plan Halsey plan Rowan plan Gantt plan ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Critical path on PERT/CPM chart is obtained by joining the events having Minimum slack No slack Average slack Maximum slack Minimum slack No slack Average slack Maximum slack ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The time by which the activity completion time can be delayed without affecting the start of succeeding activities, is known as Duration Total float Free float Interfering float Duration Total float Free float Interfering float ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The standard time for a job is Base time + relaxation time Total work content + basic time Total work content + delay contingency allowance Total work content Base time + relaxation time Total work content + basic time Total work content + delay contingency allowance Total work content ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Time study is The appraisal, in terms of time, of the value of work involving human effort Method of fixing time for workers Machine setting time Time taken by workers to do a job The appraisal, in terms of time, of the value of work involving human effort Method of fixing time for workers Machine setting time Time taken by workers to do a job ANSWER DOWNLOAD EXAMIANS APP