Industrial Engineering and Production Management A diagram showing the path followed by men and materials while performing a task is known as Travel chart String diagram Flow diagram Flow process chart Travel chart String diagram Flow diagram Flow process chart ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The time of completing a project in network analysis is given by following time of the critical activity meeting at the final triode Early start Late finish Early finish Late start Early start Late finish Early finish Late start ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Standard time is equal to Normal time taken by an operation Representative time multiplied by rating factor (Normal time) - (allowances) (Normal time) + (allowances) Normal time taken by an operation Representative time multiplied by rating factor (Normal time) - (allowances) (Normal time) + (allowances) ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Which of the following incentive plans ensures a part of the swing to the worker and rest to the employer? Taylor plan Gilbert plan Halsey premium plan Emerson efficiency plan Taylor plan Gilbert plan Halsey premium plan Emerson efficiency plan ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Routing is essential in the following type of industry Job order industry Assembly industry Process industry Mass production industry Job order industry Assembly industry Process industry Mass production industry ANSWER DOWNLOAD EXAMIANS APP