Industrial Engineering and Production Management In queuing theory, the nature of the waiting situation can be studied and analysed mathematically if All variables and constants are known and form a linear equation The laws governing arrivals, service times, and the order in which the arriving units are taken into source are known Arrival and waiting times are known and can be grouped to form a waiting line model Complete details of items in, waiting line are known All variables and constants are known and form a linear equation The laws governing arrivals, service times, and the order in which the arriving units are taken into source are known Arrival and waiting times are known and can be grouped to form a waiting line model Complete details of items in, waiting line are known ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Pick up the incorrect statement from the following. A critical ratio scheduling Adjusts automatically changes in activity progress All of the these Establishes the relative priorities among various activities on a common basis Determines the status of each activity Adjusts automatically changes in activity progress All of the these Establishes the relative priorities among various activities on a common basis Determines the status of each activity ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The start or completion of task is called None of these A duration An event An activity None of these A duration An event An activity ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The time which results in the least possible direct cost of an activity is known as Standard time Normal time Crash time Slow time Standard time Normal time Crash time Slow time ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management A big advantage of PERT over Gantt charts is that in the former case Interrelationship among activities is clearly shown Activity times are clear Early start and late finish of an activity are clearly marked Activities and events are clearly shown Interrelationship among activities is clearly shown Activity times are clear Early start and late finish of an activity are clearly marked Activities and events are clearly shown ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Standard time as compared to normal time is There is no such correlation Equal Smaller Greater There is no such correlation Equal Smaller Greater ANSWER DOWNLOAD EXAMIANS APP