In a grit chamber of a sewage treatment plant,

One minute of detention period is kept
Flow velocity 0.15 m to 0.3 m/sec is kept
Depth of 0.9 m to 1.20 m is kept
All of these

ANSWER DOWNLOAD EXAMIANS APP

Waste Water Engineering
The sewers

Must be of adequate size to avoid over flow
All listed here
Must flow under gravity ½ to ¾ full
Must be laid at least 2 to 3 m deep to collect /water from the basements