Irrigation Engineering
If L is total length of a canal in kilometers, P is total perimeter of its lining in metres and C is the cost of lining per square metre, the additional expenditure involved on lining, is

100 PLC
PL/1000C
PLC/1000
PC/100L

ANSWER DOWNLOAD EXAMIANS APP

Irrigation Engineering
In a syphon aqueduct

Canal passes over the drainage and H.F.L. of the drainage is above the bottom of the canal trough
Drainage passes over the canal and F.S.L. of the canal is above the bottom of the drainage trough
Drainage passes over the canal and F.S.L. of the canal is below the bottom of the drainage trough
Canal passes over the drainage and H.F.L. of the drainage is below the bottom of the canal trough

ANSWER DOWNLOAD EXAMIANS APP