GETCO Exam Paper (30-11-2008) If a combination of HRC fuse and a C.B. is employed, the C.B. operates for short circuit currents under all abnormal currents low over load currents this combination is never employed in practice short circuit currents under all abnormal currents low over load currents this combination is never employed in practice ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (30-11-2008) The load carrying capability of a long transmission line may be limited by stability considerations is always limited by conductor area is increased at low ambient air temperature both (a) & (b) may be limited by stability considerations is always limited by conductor area is increased at low ambient air temperature both (a) & (b) ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (30-11-2008) The delay fuses are used for protection of light circuits none of these fluorescent lamp motors light circuits none of these fluorescent lamp motors ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (30-11-2008) Interconnected power systems operating with "tie line bias" will respond to tie line load changes only both frequency and tie line load changes tie line voltage changes only frequency changes only tie line load changes only both frequency and tie line load changes tie line voltage changes only frequency changes only ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (30-11-2008) If the +Ve, -Ve & zero sequence reactances of an elements of a power system are 0.3, 0.3 & 0.8 p.u. respectively, the element would be synchronous generator static load transmission line synchronous motor synchronous generator static load transmission line synchronous motor ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (30-11-2008) Which of the following regulation is considered to be the best 0.02 0.7 0.98 0.3 0.02 0.7 0.98 0.3 ANSWER DOWNLOAD EXAMIANS APP