Power Plant Engineering Half life of a radioactive isotope corresponds to the time required for half of the following to decay Neutrons Protons Electrons Atom Neutrons Protons Electrons Atom ANSWER DOWNLOAD EXAMIANS APP
Power Plant Engineering Reflector in nuclear plants is used to Return the neutrons back into the core Conserve energy Shield the radioactivity completely Check pollution Return the neutrons back into the core Conserve energy Shield the radioactivity completely Check pollution ANSWER DOWNLOAD EXAMIANS APP
Power Plant Engineering Ferrite material is Basic raw material for nuclear plants The material which absorbs neutrons and undergoes spontaneous changes leading to the formation of fissionable material The most fissionable material The basic fuel for nuclear paints Basic raw material for nuclear plants The material which absorbs neutrons and undergoes spontaneous changes leading to the formation of fissionable material The most fissionable material The basic fuel for nuclear paints ANSWER DOWNLOAD EXAMIANS APP
Power Plant Engineering In a power station ' load center ' means Center of power plant Center of coal fields Center of gravity of electrical system Center of maximum load of equipment Center of power plant Center of coal fields Center of gravity of electrical system Center of maximum load of equipment ANSWER DOWNLOAD EXAMIANS APP
Power Plant Engineering A fast breeder reactor uses 90% U₂₃₅ Pu₂₃₉ U₂₃₈ U₂₃₅ 90% U₂₃₅ Pu₂₃₉ U₂₃₈ U₂₃₅ ANSWER DOWNLOAD EXAMIANS APP
Power Plant Engineering The fast breeder reactor uses the following moderator Carbon dioxide No moderator is used Heavy water Demineralised water Carbon dioxide No moderator is used Heavy water Demineralised water ANSWER DOWNLOAD EXAMIANS APP