GETCO Exam Paper (22-07-2015) In G-S method of power flow problem, the number of iterations _____ depends on no of buses remains fixed depends on voltage control buses depends on tolerance depends on no of buses remains fixed depends on voltage control buses depends on tolerance ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) In load flow analysis, the load at the bus is represented as a constant impedance connected at the bus none of these a voltag dependent impedance at the bus a constant current drawn from the bus a constant impedance connected at the bus none of these a voltag dependent impedance at the bus a constant current drawn from the bus ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) The constraints that are to be met with while solving UC problem are Spinning reserve all are correct Minimum down time Minimum up time Spinning reserve all are correct Minimum down time Minimum up time ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) 100% string efficiency means None uniform potential distribution across each disc Zero potential across each disc Equal potential across each disc One of the insulator discs shorted None uniform potential distribution across each disc Zero potential across each disc Equal potential across each disc One of the insulator discs shorted ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) Critical clearing time of a fault in a power system is related to Transient stability limit Short circuit limit Steady state limit Reactive power limit Transient stability limit Short circuit limit Steady state limit Reactive power limit ANSWER DOWNLOAD EXAMIANS APP