Building Construction
For providing a raft foundation, the following activities are involved1.Ramming the foundation bed2.Excavation of the soil upto required depth3.Laying the reinforcement over the foundation bed4.Curing the cement concrete placed over reinforcement5.Pouring the cement concrete over the reinforcementThe correct sequence is

1, 2, 3, 4, 5
5, 4, 3, 2, 1
2, 1, 3, 5, 4
3, 2, 5, 1, 4

ANSWER DOWNLOAD EXAMIANS APP

Building Construction
In clay soil

Consolidation continues even after several years of construction
All listed here
Differential settlement is generally prevalent
Swelling and shrinkage characteristics prevail

ANSWER DOWNLOAD EXAMIANS APP