Waste Water Engineering Disposal to sewage in large cities, is done in Purification Irrigation Oxidation Dilution Purification Irrigation Oxidation Dilution ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering The design period in years for pumping plants, is 3 to 5 1 2 to 3 5 to 10 3 to 5 1 2 to 3 5 to 10 ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering The drainage area of a town is 12 hectares. Its 40% area is hard pavement ( K = 0.85), the 40% area is unpaved streets (K = 0.20) and the remaining is wooded areas (K = 0.15). Assuming the time of concentration for the areas as 30 minutes and using the formula Ps = 900/(t + 60) the maximum run off is 0.20 cumec 0.10 cumec 0.15 cumec 0.12 cumec 0.20 cumec 0.10 cumec 0.15 cumec 0.12 cumec ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering Discrete or granular particles change their Weight Size Shape None of these Weight Size Shape None of these ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering The detention time of a circular tank of diameter d and water depth H, for receiving the sewage Q per hour, is d (0.022d + 0.085H)/Q d (0.785d + 0.011H)/Q d (0.285d + 0.011H)/Q d² (0.011d + 0.785H)/Q d (0.022d + 0.085H)/Q d (0.785d + 0.011H)/Q d (0.285d + 0.011H)/Q d² (0.011d + 0.785H)/Q ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering A manhole is generally provided at each All of these Change of gradient Junction Bend All of these Change of gradient Junction Bend ANSWER DOWNLOAD EXAMIANS APP