Construction Planning and Management If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then expected time of activity A is greater than the expected time of activity B None of these expected time of activity B is greater than the expected time of activity A expected time of both activities A and B are same expected time of activity A is greater than the expected time of activity B None of these expected time of activity B is greater than the expected time of activity A expected time of both activities A and B are same ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is a weakness of bar chart? Project progress Uncertainties All of these Interdependencies of activities Project progress Uncertainties All of these Interdependencies of activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For completion of a project, the critical path of the network represents Maximum cost Minimum time Minimum cost Maximum time Maximum cost Minimum time Minimum cost Maximum time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A machine is purchased for Rs. 10,000,00 and has an estimated life of 10 years. The salvage value at the end of 10 years is Rs. 1,50,000. The book value of the machine at the end of 5 years using general straight line method of evaluation of depreciation is Rs. 8,50,000 Rs. 6,50,000 Rs. 4,75,000 Rs. 5,75,000 Rs. 8,50,000 Rs. 6,50,000 Rs. 4,75,000 Rs. 5,75,000 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following excavators is most suitable for digging under water? Drag line Hoe Dipper shovel Clam shell Drag line Hoe Dipper shovel Clam shell ANSWER DOWNLOAD EXAMIANS APP