MGVCL Exam Paper (30-07-2021 Shift 3)
Consider a solar PV plant with the following specific conditions:
Analysis period: 1 year
Measured average solar irradiation intensity in 1 year: 150 kWh/m²
Generator area of the PV plant: 10 m² Efficiency factor of the PV modules: 15%
Electrical energy actually exported by plant to grid: 135 kWh
Calculate the performance ratio.

75%
80%
50%
60%

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 3)
Which among these components connects to physical equipments of the distribution system?

Central control room with host computers
None of these
Remote Terminal Unit
Communication infrastructure

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 3)
The sites where the capacity factor is ____ are not considered suitable for wind power generation.

less than 12%
greater than 12%
greater than 24%
less than 24%

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP