Building Construction As compared to stretcher course, the thickness of joints in header course should be More Less Equal or more Equal More Less Equal or more Equal ANSWER DOWNLOAD EXAMIANS APP
Building Construction The additional piles which are driven to increase the capacity of supporting loads on vertical piles, are known Sinking piles Construction piles Raking piles Eccentric piles Sinking piles Construction piles Raking piles Eccentric piles ANSWER DOWNLOAD EXAMIANS APP
Building Construction The vertical member running through middle of a shutter frame, is Style Post Mullion Reveal Style Post Mullion Reveal ANSWER DOWNLOAD EXAMIANS APP
Building Construction The form Work including the props can be removed from beams, only after 21 days 3 days 7 days 14 days 21 days 3 days 7 days 14 days ANSWER DOWNLOAD EXAMIANS APP
Building Construction The thickness of a reinforced brick partition wall, is generally kept 10 cm 5 cm 15 cm 20 cm 10 cm 5 cm 15 cm 20 cm ANSWER DOWNLOAD EXAMIANS APP
Building Construction Depth of lean concrete bed placed at the bottom of a wall footing, is kept Less than its projection beyond wall base 10 cm 15 cm Equal to its projection beyond wall base Less than its projection beyond wall base 10 cm 15 cm Equal to its projection beyond wall base ANSWER DOWNLOAD EXAMIANS APP