Measurement and Instrumentation
A variable w is related to three other variables x, y and z as w = xy/z. The variables are measured with meters of accuracy ± 0.5% reading, ± 1% of full scale value and ± 1.5% reading. The actual readings of the three meters are 80, 20 and 50 with 100 being the full scale value for all three. The maximum uncertainty in the measurement of w will be

 ± 7%
 ± 6%
 ± 5%
 ± 8%

ANSWER DOWNLOAD EXAMIANS APP

Measurement and Instrumentation
The time/div and voltage axes of an oscilloscope have been creased. A student connects a 1 KHz, 5 V P-P square wave calibrition pulse to channel-1 of the scope and observes the screen to be as shown in the upper trace of figure. An unknown signal is connected to channel-2 (lower trace) of the scope. If the time/div and V/div on both channels are the same, the amplitude (P-P) and period of the unknown signal are respectively

 5 V, 2 ms.
 5 V, 1 ms.
  7.5 V, 2 ms.
 10 V, 1 ms.

ANSWER DOWNLOAD EXAMIANS APP