Power Systems
A power generating station has a maximum demand of 1000 MW. The annual load factor is 75% and plant capacity factor is 60%. Calculate the reserve capacity?

 1250 MW
 500 MW
 250 MW
 750 MW

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
The advantage of hydro electric power station over thermal power station is

 hydro electric station can be constructed at the place where the energy is required
 the operation cost of hydro electric power station is low
 the initial cost of hydro electric power station is low
 hydro electric power station can supply the power throughout the year

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
A lossless power system has to serve a load of 250 MW. There are two generators(G1 and G2) in the system with cost curves C1 and C2 respectively defined as follows: C1 = PG1+0.055P²G1 C2 = 3 PG2 + 0.03 P²G2 Where PG1 and PG2 are the MW injections from generators G1 and G2 respectively. Thus, the minimum cost dispatch will be

 PG1 = 0 MW and PG2 = 250 MW
 PG1 = 150 MW and PG2 = 100 MW
 PG1 = 100 MW and PG2 = 150 MW
 PG1 = 250 MW and PG2 = 0 MW