Power Systems
A power generating station has a maximum demand of 1000 MW. The annual load factor is 75% and plant capacity factor is 60%. Calculate the reserve capacity?

 750 MW
 250 MW
 1250 MW
 500 MW

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
The incremental fuel costs for two generating units G1 and G2 are given by Ic1 = 25 + 0.2 PG1 and Ic2 = 32 + 0.2 PG2, where PG1 and PG2 are real powers generated by the units. The economic allocation for a total load of 250 MW, neglecting transmission loss, is given by

 PG1 = 125 MW and PG2 = 125 MW
 PG1 = 142.5 MW and PG2 = 107.5 MW
 PG1 = 109.75 MW and PG2 = 140.25 MW
 PG1 = 100 MW and PG2 = 150 MW

ANSWER DOWNLOAD EXAMIANS APP