Power Systems A power generating station has a maximum demand of 1000 MW. The annual load factor is 75% and plant capacity factor is 60%. Calculate the reserve capacity? 1250 MW 500 MW 250 MW 750 MW 1250 MW 500 MW 250 MW 750 MW ANSWER DOWNLOAD EXAMIANS APP
Power Systems Deflectors are provided in Kaplan turbine. Pelton wheel. propeller turbine. Francis turbine. Kaplan turbine. Pelton wheel. propeller turbine. Francis turbine. ANSWER DOWNLOAD EXAMIANS APP
Power Systems A generating station has a maximum demand of 100 MW, a load factor of 60% and a plant capacity factor of 50%. The reserve capacity of the plant is 10 MW 80 MW 20 MW 15 MW 10 MW 80 MW 20 MW 15 MW ANSWER DOWNLOAD EXAMIANS APP
Power Systems The advantage of hydro electric power station over thermal power station is hydro electric station can be constructed at the place where the energy is required the operation cost of hydro electric power station is low the initial cost of hydro electric power station is low hydro electric power station can supply the power throughout the year hydro electric station can be constructed at the place where the energy is required the operation cost of hydro electric power station is low the initial cost of hydro electric power station is low hydro electric power station can supply the power throughout the year ANSWER DOWNLOAD EXAMIANS APP
Power Systems Which of following power plants will take long period in erection and installation Thermal. Nuclear. Gas turbine. Hydro Power Plant Thermal. Nuclear. Gas turbine. Hydro Power Plant ANSWER DOWNLOAD EXAMIANS APP
Power Systems A lossless power system has to serve a load of 250 MW. There are two generators(G1 and G2) in the system with cost curves C1 and C2 respectively defined as follows: C1 = PG1+0.055P²G1 C2 = 3 PG2 + 0.03 P²G2 Where PG1 and PG2 are the MW injections from generators G1 and G2 respectively. Thus, the minimum cost dispatch will be PG1 = 0 MW and PG2 = 250 MW PG1 = 150 MW and PG2 = 100 MW PG1 = 100 MW and PG2 = 150 MW PG1 = 250 MW and PG2 = 0 MW PG1 = 0 MW and PG2 = 250 MW PG1 = 150 MW and PG2 = 100 MW PG1 = 100 MW and PG2 = 150 MW PG1 = 250 MW and PG2 = 0 MW ANSWER DOWNLOAD EXAMIANS APP