Industrial Engineering and Production Management A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is 0.84 0.5 0.66 0.95 0.84 0.5 0.66 0.95 ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management A dummy activity Is artificially introduced Does not require any time All of the these Is represented by a dotted line Is artificially introduced Does not require any time All of the these Is represented by a dotted line ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management According to MAPI formula, the old machine should be replaced by new one when (Here, CAM = Challenger's Adverse minimum, DAM = Defender's Adverse minimum) CAM < DAM CAM > DAM There is no such criterion CAM = DAM CAM < DAM CAM > DAM There is no such criterion CAM = DAM ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Work study involves Only motion study Only work measurement Method study and work measurement Only method study Only motion study Only work measurement Method study and work measurement Only method study ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management In the Halsey 50-50 plan, the following are rewarded more Past poor workers All of the these Past average workers Past good workers Past poor workers All of the these Past average workers Past good workers ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management In jobbing production All of these Unit costs are high Operations are labour-intensive Highly skilled workers are needed All of these Unit costs are high Operations are labour-intensive Highly skilled workers are needed ANSWER DOWNLOAD EXAMIANS APP