Industrial Engineering and Production Management A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is 0.95 0.66 0.84 0.5 0.95 0.66 0.84 0.5 ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The linear programming techniques can be applied successfully to industries like Iron and steel Food processing Oil and chemical All of the listed here Iron and steel Food processing Oil and chemical All of the listed here ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management In PERT analysis, critical path is obtained by joining events having Zero slack -ve slack Dummy activities +ve slack Zero slack -ve slack Dummy activities +ve slack ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management String diagram is used when Material handling is to be done Team of workers is working at a place All of these Idle time is to be reduced Material handling is to be done Team of workers is working at a place All of these Idle time is to be reduced ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management An event is indicated on the network by A straight line A straight line with circles at the ends A number enclosed in a circle or a square A dotted line A straight line A straight line with circles at the ends A number enclosed in a circle or a square A dotted line ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Pessimistic time is The maximum time which an activity might require The average time required for a job The most probable time considering all conditions The minimum time in which an activity can possibly be accomplished The maximum time which an activity might require The average time required for a job The most probable time considering all conditions The minimum time in which an activity can possibly be accomplished ANSWER DOWNLOAD EXAMIANS APP