Industrial Engineering and Production Management A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is 0.95 0.5 0.66 0.84 0.95 0.5 0.66 0.84 ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management CPM requires Double time estimate None of these Triple time estimate Single time estimate Double time estimate None of these Triple time estimate Single time estimate ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Work sampling observations are taken on the basis of Past experience Convenience Table of random numbers Detailed calculations Past experience Convenience Table of random numbers Detailed calculations ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Which of the following organisation is preferred in automobile industry? Functional organisation Staff organisation Line organisation Line and staff organizations Functional organisation Staff organisation Line organisation Line and staff organizations ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Work study is done with the help of Material handling Process chart All of the these Stop watch Material handling Process chart All of the these Stop watch ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management In CPM, the cost slope is determined by Normal Cost/Crash cost (Normal cost - Crash cost)/ (Normal time - Crash time) (Crash Cost - Normal cost)/ (Normal time - Crash time) Crash cost/Normal Cost Normal Cost/Crash cost (Normal cost - Crash cost)/ (Normal time - Crash time) (Crash Cost - Normal cost)/ (Normal time - Crash time) Crash cost/Normal Cost ANSWER DOWNLOAD EXAMIANS APP