Engineering Economics
A manufacturing firm maintains one product assembly line to produce signal generators. Weekly demand for the generators is 35 units. The line operates for 7 hours per day, 5 days per week. What is the maximum production time per unit in hours required of the line to meet the demand?

1.0 hour per unit
1.2 hours per unit
1.4 hours per unit
1.6 hours per unit

ANSWER DOWNLOAD EXAMIANS APP

Engineering Economics
A telephone switchboard 100 pair cable can be made up with either enameled wire or tinned wire. There will be 400 soldered connections. The cost of soldering a connection on the enameled wire will be P 1.65 on the tinned wire, it will be P 1.15. A 100- pair cable made up with enameled wire cost P 0.55 per linear foot and those made up of tinned wire cost P 0.75 per linear foot. Determine the length of cable run in feet so that the cost of each installation would be the same.

1,000 feet
1,040 feet
1,100 feet
1,120 feet

ANSWER DOWNLOAD EXAMIANS APP