Power Systems A 100 MVA alternator operating at full load at 50 Hz. H = 4 MWsec/MVA, Td = 0.5 sec. One of the transmission line is tripped. So that output of generator is reduced to 70 MW. Find the frequency deviation during this time? -0.92 0.56 -0.56 0.92 -0.92 0.56 -0.56 0.92 ANSWER DOWNLOAD EXAMIANS APP
Power Systems If the time of operation of a relay for unity TMS is 10 sec. the time of operation of 0.5 TMS will be _______________ secs. 20. 5. 3. 7. 20. 5. 3. 7. ANSWER DOWNLOAD EXAMIANS APP
Power Systems For load flow studies, What are the quantities specified at load bus are δ and Q P and Q P and V V and δ δ and Q P and Q P and V V and δ ANSWER DOWNLOAD EXAMIANS APP
Power Systems Which of the following matrix is used for load flow studies? null matrix Z bus matrix Unit matrix Y bus matrix null matrix Z bus matrix Unit matrix Y bus matrix ANSWER DOWNLOAD EXAMIANS APP
Power Systems An isolated synchronous generator with transient reactance equal to 0.1 pu on a 100 MVA base is connected to the high voltage bus through a step up transformer of reactance 0.1 pu on a 100 MVA base. The fault level at the bus is 500 MVA 200 MVA 100 MVA 400 MVA 500 MVA 200 MVA 100 MVA 400 MVA ANSWER DOWNLOAD EXAMIANS APP
Power Systems Mho relay is usually employed for protection of any line long transmission lines only medium transmission lines only short transmission lines only any line long transmission lines only medium transmission lines only short transmission lines only ANSWER DOWNLOAD EXAMIANS APP